Sunrise Drive stayed open during record-breaking storms over the Halloween weekend, thanks to a recently completed drainage structure at Esperero Wash.

The six-cell concrete box culvert, built by Pima County Transportation, channeled stormwater through the wash and away from the road during the Oct. 31–Nov. 2 storms, the county said in a Nov. 12 statement. In previous years, sediment buildup at the crossing often caused rain and debris to flow onto Sunrise Drive during the monsoon. Without the new culvert, the road normally would have had to close during a severe storm, the county said.

Rain broke daily records across the greater Tucson area on Oct. 31, Nov. 1 and Nov. 2, according to the county. Parts of Mount Lemmon received more than 8 inches over those three days.

Josh Orth, project manager at Pima County Project Design & Construction, said the culvert project took six months and was completed while two-way traffic continued on the busy road.

"Despite the complexity of the work, there were no traffic delays and not a single complaint from the public," Orth said.

Orth said he received several calls from constituents who appreciated the results.

Video footage provided to county staff shows the culvert handling the stormwater as designed.

The Cañada del Oro Wash, along with the Santa Cruz River, Sabino Creek, the Rillito River and Alamo Wash, recorded their highest flows of 2026 during the weekend storms, according to Pima County Flood Control. The county's bank protection held, and none of those waterways overflowed.

Since the flood of 1983, Pima County has built more than 101 miles of embankments around local waterways to guard against storm-related flooding, the county said.